Living Edge Stage 1, 1B & 3

Location: Woolcoot Road, Wellard

Client: Parcel Property
Consultant: Pritchard Francis
Scope of works: Civil Works, Headworks
Value of works: $2.8 million

 

Description of works:
Buckby Contracting completed the first 3 stages of Living Edge for Parcel Property. To date, approximately 60 lots are delivered. The first stage involved bringing over 1,500 m of water, power and gas services to the subdivision. It also included connecting an existing sewer to a neighbouring subdivision.

The site involved some dewatering, treatment of ASS and management of soils. The roundabout was constructed under half road closure and a road upgrade (lifting and partial widening) along Woolcoot Road has been completed as part of the civil works. The projects have all been completed on time.